THE PROJECT COMPRISED OF THE CONSTRUCTION OF A NEW WAREHOUSE AND PRODUCTION AREA BUILDING TOGETHER WITH AN ATTACHED TWO STOREY OFFICE BUILDING. THE BUILDINGS WERE CONSTRUCTED ON A SLOPING 'GREENFIELD' SITE
The warehouse and production area building was constructed using a single storey steel framed structure clad with curved insulated roof cladding and insulated wall cladding. The office building was constructed using a two storey steel framed structure with curved insulated roof cladding and an external envelope comprising of a combination of facing brickwork, insulated wall cladding and aluminium windows and entrance doors. The project included the construction of the external car parking and paved areas, landscaping, drainage and services
Key features of the project were:-
- Steel framed structures
- Retaining wall construction to accommodate the sloping site
- Curved insulated roof cladding